Number: 1254
Post date: March 30, 2023
Name: Craig Johnson
Department: Building Operations
Email: cjohnson@ksu.edu [2]
Phone: (785) 532-6591
Type of Problem: Cosmetic
Priority: Address When Possible
The new conduit for the AV system needs to be painted the gray color of the wall paint. The AV is scheduled to be install some time after April 10, and the painting should be finished prior to the system installation.
Specific Location: 2 - 224 - Room 224
Requested Deadline?: April 8, 2023
Progress Level: Completed